Blue Chip II Gaming Vessel, Boyd Gaming Corporation
Michigan City, IN
Type of Work: Heating and Air Conditioning, Process Piping
Architect/Engineer:
Guido Perla & Associates
Contract Amount: $16.3 million
When Boyd Gaming considered a new casino boat to replace an aging, overcrowded one in Michigan City, Ind., they took on the two top criticisms voiced by patrons of many floating casinos: lack of fresh air in the smoke-filled gaming rooms, and congestion in the too-narrow spaces between tables and slot machines.
The Las Vegas gaming company’s new Blue Chip Casino boat, near the shore of southern Lake Michigan, would not only be spacious – it would be the world’s largest. But the ship’s initial plan encountered rough water early, when estimators put its cost at $200 million, nearly twice what the owner originally thought it would cost.
To meet their budget, the size would have to be reduced from five decks to four, a step that would significantly affect the ship’s piping systems. International Piping Systems, Inc. came to the owner’s aid. IPS CEO Robert Lempa, Vice President of Sales Greg Maus and Project Manager Dave Sawtell flew from their Chicago-area office to both coasts to help the project’s marine architect (Guido-Perla Associates, Seattle, Wash.) and shipbuilder (Jamestown Metal Marine Sales, Inc., Boca Raton, Fla.) downsize the mechanical systems. They were assisted by IPS Indiana office Estimator Brian Lecea and KJWW Engineering, a mechanical engineering firm in Naperville, Ill. “We fine tuned everything related to HVAC on the vessel,” Maus said.
The owner recognized IPS’s commitment and expertise early in the project, and when it came time to build, named IPS the lead mechanical contractor. Unlike projects on dry land, where every detail is drawn before assembled, much of boat building takes place “on the fly.” Consequently, the project’s design phase often overlapped the construction phase, so IPS had to build one part of the ship before other parts were even on the drawing board. The mechanical contractor’s planning and scheduling mastery were also challenged. The ship’s heavy-duty chillers, boilers, generators and other components and piping had to be set inside the 160,000 square-foot hull in a choreographed sequence that kept in step with the shipbuilder.
Staying in step meant getting materials delivered on time and in the right sequence. Piping assemblies were prefabricated (onsite and off) as much as possible. Material handling was a daily priority as everything had to be scheduled around availability of the busy cranes. The IPS crew made a rubber tire fork truck, or “Lull,” their workhorse, running it non-stop to set everything they needed alongside the boat for hoisting. When possible they set sections of large pipe on temporary supports inside the hull, to avoid a second, more difficult lift when the deck from which it would hang was finally built. “We had to fit everything in between crane lifts. That was the biggest challenge,” said Frank Camasta, project superintendent for IPS.
IPS is proud of its part in getting the Blue Chip Casino boat first on the drawing board and then into the water. The careful, detailed approach brought to the planning table was sustained throughout the construction phase. When it opened in Jan. 2006, the 400-foot-long Blue Chip could still lay claim as the world’s largest and roomiest casino boat. Its extra-wide gambling rooms with tall ceilings and majestic décor have more the look of a grand hotel ballroom than a gambling boat. And with a high-end HVAC system capable of 15 full indoor air changes per hour, it’s also the freshest and most comfortable.
You can read the JobScope feature story about the Blue Chip project by clicking here (PDF/670K).